AXENS – Catalyst production

AXENS – Catalyst production

Implementation of a new catalyst production line in an existing workshop
Location: Salindres, Gard FRANCE
Project phase: Studies and implementation
Project duration: 18 months

EVERE – Fos-sur-Mer

EVERE – Fos-sur-Mer

Audit, improvement, reliability and debottlenecking of the wastewater treatment plant
Location : Fos-sur-Mer (13)
Project phases: Feasibility studies
Study period: 2 months

ARKEMA – Effluent treatment

ARKEMA – Effluent treatment

Treatment of effluents from the Pierre Bénite plant
Location: Pierre Bénite (69)
Project phases: Diagnosis, Project Management Assistance, EPCM
Project duration: 18 months

CARBONE SAVOIE – Smoke treatment

CARBONE SAVOIE – Smoke treatment

Implementation of smoke treatment for all existing furnaces
Location: Vénissieux, Rhône, FRANCE
Project phase : Studies and implementation
Project duration : 18 months