Other Archives - Emdelen https://emdelen.fr/en/category/other/ Designing today the industrial facilities of the future Fri, 14 Feb 2020 11:01:39 +0000 en-GB hourly 1 https://emdelen.fr/wp-content/uploads/2018/10/cropped-LogoRVB_marge-droite-32x32.png Other Archives - Emdelen https://emdelen.fr/en/category/other/ 32 32 COLEMAN – Modifications of gas distribution networks https://emdelen.fr/en/coleman-gas-distribution-networks/?utm_source=rss&utm_medium=rss&utm_campaign=coleman-gas-distribution-networks Thu, 14 Feb 2019 12:55:38 +0000 https://emdelen.fr/?p=3265 Modifications to the propane and butane distribution networks to take into account the new PPRT (Technological risk prevention plan)
Location: Saint-Genis Laval (69)
Project Phases: Detailed design study
Study period: 4 months

L’article COLEMAN – Modifications of gas distribution networks est apparu en premier sur Emdelen.

]]>

Modifications to the propane and butane distribution networks to take into account the new PPRT (Technological risk prevention plan)

Location: Saint-Genis Laval (69)
Project Phases: Detailed design study
Study period: 4 months

Context of the project: Coleman required works on a set of equipment intended to supply liquefied gases (butane, propane and propane/butane mixture) to machines producing liquefied gas cartridges for outdoor activities (camping). This work follows the establishment of a PPRT (Technological risk prevention plan).

Emdelen Mission: Detailed Preliminary Project Study prior to the execution of the work

  • Scope of the study
    • Relocation and modification of the existing pump house
    • Replacement of the propane/butane mixer
    • Definitions of the diameters of the new networks
    • Passage of gas networks through technical galleries covered with sand
    • Replacement of the manual gas cartridge emptying station by a semi-automatic station
    • Replacement of the obsolete gas cooler with insufficient capacity
  • Emdelen services:
    • Study of the pump house, optimization of the number of LPG pumps, definition of pump performances
    • Study of a new propane/butane mixing system
    • Study of a new gas cartridge emptying system with liquefied gas recovery and reduction of the vaporized fraction.
    • Study of the cathodic protection of networks in channel by impressed current
    • Establishment of PIDs and functional analysis
    • Specification and consultation of equipment and work
    • Analysis and alignment of offers
    • 3D model of the installation
    • Site plans and guide plans
    • Planning and Capex (€3m)

Total amount of the project :

Range A < €10 million
Range B: between €10 and €20 million
Range C: between €20 and €50 million
Range D > €50 million

You can find our different realizations in others industries by clicking on the following link.

L’article COLEMAN – Modifications of gas distribution networks est apparu en premier sur Emdelen.

]]>
EMILE NOEL Oil Mill – Feasibility transfer industrial https://emdelen.fr/en/oil-mill-feasibility-transfer-industrial/?utm_source=rss&utm_medium=rss&utm_campaign=oil-mill-feasibility-transfer-industrial Thu, 14 Feb 2019 11:01:17 +0000 https://emdelen.fr/?p=3211 Feasibility engineering preliminary to an industrial transfer of a seed crushing unit, oil conditioning and associated liquid and solid storage.
Location : Pont-Saint-Esprit, Gard FRANCE
Project Phase : Feasibility study (Master Plan)
Project Duration : 4 months

L’article EMILE NOEL Oil Mill – Feasibility transfer industrial est apparu en premier sur Emdelen.

]]>

Feasibility engineering preliminary to an industrial transfer of a seed crushing unit, oil conditioning and associated liquid and solid storage.

Location : Pont-Saint-Esprit, Gard FRANCE
Project Phase : Feasibility study (Master Plan)
Project Duration : 4 months

The oil mill Emile Noel started as a family business in the 1920 and became the EMILE group in 2018 and now offers a range of products from the oilseed sector: organic vegetable edible oils, vinegars and cosmetics.

Located in Pont-Saint-Esprit, the oil mill EMILE NOEL is an important player in the French organic oil market. The company wanted to anticipate and prepare its future evolution by transferring its presses located on site in a very old building to a new facility. The transfer of the presses led to the general redevelopment of the site. For this purpose, the Company preferred to rely on the services of industrial engineering to complete and confirm the upstream architectural studies.

Studies :

  • Sizing of seed and oil storage facilities
  • Process diagrams and diagrams
  • Proposal of 2 locations (1 in existing building, 1 in new building):
    • Staff flows
    • Material flow (no crossing of certain flows)
    • Maintainability
    • Possibility of evolution towards automated storage
    • Integration of supplier packages: new turnkey storage and new turnkey crushing lines
  • Justification note of the engineering choices and descriptions of the planned lots: process (equipment), building (covered enclosure), light work and HVAC
  • Electrical power assessment and associated architecture
  • CAPEX
  • Planning

Lots concerned :

  • Presses
  • Associated utilities (steam, compressed air, hot and cold water)
  • Seed storage
  • Oil storage
  • Building and light work
  • Control room
  • Tooling stores
  • Receiving and shipping stores
  • Storage of raw materials and finished products (bulk silos, big-bags, drums)
  • Parking
  • Heavy roads with turning areas

Other EMDELEN services :

  • Technical meetings with the architect and the project owner
  • Technical meetings with suppliers (storage and pressing lines)
  • Studies of utilities, all fluids, electricity Strong and weak currents, computer networks

Total amount of the project :

Range A < €10 million
Range B: between €10 and €20 million
Range C: between €20 and €50 million
Range D > €50 million

You can find our different realizations in others industries by clicking on the following link.

L’article EMILE NOEL Oil Mill – Feasibility transfer industrial est apparu en premier sur Emdelen.

]]>
LORD Fly By Wire – Preliminary engineering https://emdelen.fr/en/lord-fly-by-wire-preliminary-engineering/?utm_source=rss&utm_medium=rss&utm_campaign=lord-fly-by-wire-preliminary-engineering Fri, 15 Feb 2019 10:33:24 +0000 https://emdelen.fr/?p=3369 Preliminary engineering for an industrial transfer of a manufacturing and maintenance unit for flight control systems.
Location: Saint Vallier, Drôme FRANCE
Project phase: Studies
Project duration: 6 months

L’article LORD Fly By Wire – Preliminary engineering est apparu en premier sur Emdelen.

]]>

Preliminary engineering for an industrial transfer of a manufacturing and maintenance unit for flight control systems.

Location: Saint Vallier, Drôme FRANCE
Project phase: Studies
Project duration: 6 months

Bought from SKF Aerospace in 2016 by the American group Lord Corporation, Fly by Wire, renamed Lord Solutions France in 2018, designs and manufactures cockpit control systems, from receivers to electromechanical actuators that activate pilot controls.

Fly by Wire Systems France, located in Saint Vallier, the world leader in cockpit equipment for aircraft, wanted to anticipate and prepare its relocation to a site it had just acquired by relying on the services of an industrial engineering company to complete and confirm the upstream architectural studies.

Studies :

  • Synthesis of flow studies conducted upstream by Fly by Wire Systems France
  • First study of the new premises taking into account the constraints:
    • Staff flows
    • Material flow (no crossing of certain flows)
    • Maintainability
  • Possibility of moving towards automated storage
  • Presentations of these studies to the other project actors, architect, promoter, project manager
  • Final implementation study
  • Interface tables for all fluids, high and low current electricity, ESP (electronic stability program)
  • Interface positioning plan
    • Lots concerned:
    • Machining
    • NDT
    • 3D control
    • Entry control
    • Tooling stores
    • Receiving and shipping stores
    • Storage of raw materials
    • Electronic workshop

Other Emdelen services :

  • Technical meetings with the developer, architect and project owner
  • Technical meetings with suppliers (automated storage systems)
  • Studies of utilities, all fluids, electricity strong and weak currents, computer networks

Total amount of the project :

Range A < €10 million
Range B: between €10 and €20 million
Range C: between €20 and €50 million
Range D > €50 million

You can find our different realizations in others industries by clicking on the following link.

L’article LORD Fly By Wire – Preliminary engineering est apparu en premier sur Emdelen.

]]>
ESOPP Engineering – Studies – Plastic Packaging Films https://emdelen.fr/en/esopp-engineering-studies/?utm_source=rss&utm_medium=rss&utm_campaign=esopp-engineering-studies Thu, 14 Feb 2019 12:15:54 +0000 https://emdelen.fr/?p=3207 Engineering studies of piping and cable routing
Location: Chambéry Savoie FRANCE
Project phase: Engineering studies
Project duration: 6 months

L’article ESOPP Engineering – Studies – Plastic Packaging Films est apparu en premier sur Emdelen.

]]>

Engineering studies of piping and cable routing

Location: Chambéry Savoie FRANCE
Project phase: Engineering studies
Project duration: 6 months

ESOPP manufactures production lines for plastic packaging films, used in the food industry, but also in the high-tech industry for lithium-ion batteries. ESOPP generates almost all of its sales revenue from exports, particularly to China, Turkey, Africa, North America and India.

For a project in Nigeria, ESOPP wished to be assisted early in the project for the piping and cable routing study. This strategy made possible the anticipation of the purchase and prefabrication of piping, supports, cables and cable trays.

Studies carried out:

  • Finalization of fluid PIDs, line numbering (about 270 lines), selection of piping classes
  • Finalization of engine lists (about 300) and instrumentation
  • Realization of cable notebooks
  • Realization of cable routing notebooks, dimensioning of cable tray sections
  • Realization of a complete model of the installation
    • Integration of civil engineering and building guide plans
    • Recovery of ESOPP machine envelopes and fluid interface points
    • Installation of the machines in the model
    • Carrying out studies of piping, pipe support and cable trays according to the upstream studies (PID, cable trays booklet)
  • Extraction of isometrics from pipes and ventilation ducts with detailed nomenclatures
  • Nomenclature of pipes by class and diameter for preparation of purchase consultations
  • Nomenclature of cables based on actual measurements from the model and routing
  •  

Total amount of the project:

Range A < €10 million
Range B: between €10 and €20 million
Range C: between €20 and €50 million
Range D > €50 million

You can find our different realizations in others industries by clicking on the following link.

L’article ESOPP Engineering – Studies – Plastic Packaging Films est apparu en premier sur Emdelen.

]]>
SPMR – Fire Protection Network https://emdelen.fr/en/spmr-fire-protection-network/?utm_source=rss&utm_medium=rss&utm_campaign=spmr-fire-protection-network Thu, 14 Feb 2019 12:12:59 +0000 https://emdelen.fr/?p=3204 Construction of the fire protection network for a fuel depot
Location: Villette-de-Vienne (38)
Project phases: engineering study, implementation and commissioning
Project duration: 36 months

L’article SPMR – Fire Protection Network est apparu en premier sur Emdelen.

]]>

Construction of the fire protection network for a fuel depot

Location: Villette-de-Vienne (38)
Project phases: engineering study, implementation and commissioning
Project duration: 36 months

Project background: Based on the fire protection study defined by ODZ Consultants, EMDELEN designed and implemented the entire system to ensure the detection and fire protection of the SPMR site (fuel storage).

Studies for the fire protection network :

  • Definition and management of fire scenarios
  • Assessment, sizing of equipment and drafting of technical specifications
  • Implementation of the entire protection system
  • Specification of the work (civil engineering, steel structures, piping, EIA)
  • Consulting, technical alignment and supplier selection
  • CAPEX and planning

Implementation and start-up: Mission of EPCM

  • Follow-up of the execution studies of all suppliers (works and equipment)
  • Follow-up of the planning
  • Site supervision
  • Reception of installations
  • Testing and start-up

Total amount of the project : 

Range A < €10 million
Range B: between €10 and €20 million
Range C: between €20 and €50 million
Range D > €50 million

Notice point : Installation of a set of 3 diesel motor pumps with Q= 1500 m3/h and P = 12 bar each for a total of 1 MW thermal; and piping network > 2 km.

You can find our different realizations in others industries by clicking on the following link.

L’article SPMR – Fire Protection Network est apparu en premier sur Emdelen.

]]>
SOLO – Waste Gasification Plant https://emdelen.fr/en/solo-waste-gasification-plant/?utm_source=rss&utm_medium=rss&utm_campaign=solo-waste-gasification-plant Thu, 14 Feb 2019 12:08:30 +0000 https://emdelen.fr/?p=3202 Installation of a waste gasification plant and electricity production
Location: Solo, Indonesia
Project phase: Engineering studies
Project duration: 12 months

L’article SOLO – Waste Gasification Plant est apparu en premier sur Emdelen.

]]>

Installation of a waste gasification plant and electricity production

Location: Solo, Indonesia
Project phase: Engineering studies
Project duration: 12 months

Context of the project: the city of Solo wanted to recover its waste by producing electricity from a gasification process. EMDELEN’s mission was to design the entire waste treatment chain from the arrival of the collections to energy recovery by integrating waste preparation, gasification process, syngas purification, thermal engines, automatic engine safety chain and all utilities

Key figures: 260000 tonnes/year of waste, recovery of 10 MWe

Studies :

  • Complete design of the “Waste preparation” section
  • Proposal of several technical solutions for the recovery of energy from hot syngas and exhaust gases from internal combustion engines
  • Equipment assessments and sizing
  • 3D design and implementation of the entire plant
  • Drafting of technical specifications for equipment sets (including work)
  • OPEX

Total amount of the project :

Range A < €10 million
Range B: between €10 and €20 million
Range C: between €20 and €50 million
Range D > €50 million

Special note: Integration of an innovative technology for biomass valorisation 

You can find our different realizations in others industries by clicking on the following link.

L’article SOLO – Waste Gasification Plant est apparu en premier sur Emdelen.

]]>